42
            
          
        
        
          
            Geotechnical News • March 2016
          
        
        
        
          
            THE GROUT LINE
          
        
        
          and the drainage of the embankment
        
        
          through the up-stream face after the
        
        
          reservoir draw-down.
        
        
          In order to limit potential damage
        
        
          to the core and to avoid the risk of
        
        
          heave, the injections commenced
        
        
          with a relatively modest GIN value
        
        
          of 1,000. The early section of the
        
        
          works was phased so that the grouting
        
        
          engineer could very quickly observe
        
        
          the effectiveness of the ground treat-
        
        
          ment over the primary and secondary
        
        
          phases for a limited section of both
        
        
          the upstream and downstream grout
        
        
          curtain. The reduction ratio achieved
        
        
          for the grout volumes injected in the
        
        
          four successive phases was lower
        
        
          than was anticipated, and the GIN
        
        
          value was therefore increased to 1,200
        
        
          to allow slightly greater pressures
        
        
          and greater maximum volumes to
        
        
          be applied for the remainder of the
        
        
          works, whilst retaining the same target
        
        
          volume per linear metre, and the same
        
        
          limiting maximum pressure. A single
        
        
          GIN value was selected for the entire
        
        
          works.
        
        
          At Carno, the GIN system was applied
        
        
          with particular care, partly because of
        
        
          the reduced confinement arising from
        
        
          the reservoir draw-down, and partly
        
        
          to ensure that the results at the end of
        
        
          the secondary phase met the specified
        
        
          requirements, with no requirement
        
        
          for a tertiary phase. The software
        
        
          displayed real-time plots of basic
        
        
          injection parameters, together with an
        
        
          additional completion criterion, - the
        
        
          ‘Equivalent Lugeon’ value. This value
        
        
          combined the volume, pressure, and
        
        
          time data for the injection in progress,
        
        
          and calculated an Equivalent Lugeon
        
        
          value, by taking into consideration
        
        
          the relative viscosity of the grout
        
        
          mix to that of water. This function
        
        
          was clearly not a true Lugeon value,
        
        
          but a close estimation for fluidified
        
        
          and stable grout, which allowed the
        
        
          progressive evolution of the effective
        
        
          Lugeon value, and hence the progres-
        
        
          sive reduction in transmissivity of the
        
        
          rock, to be observed in real-time as the
        
        
          injection progresses, similar to con-
        
        
          tinuous water test, but with grout.
        
        
          In the typical example illustrated in
        
        
          Figure 2, it can be observed that at
        
        
          the end of the injection the pressure
        
        
          increases and flow rate reduces - clear
        
        
          evidence that the rock is “tightening-
        
        
          up’; but also that the injection has
        
        
          continued until the Equivalent Lugeon
        
        
          value has fallen below the speci-
        
        
          fied maximum allowable value of 3
        
        
          Lugeons. However, if the same graph-
        
        
          ics are plotted against a timescale,
        
        
          Figure 2 (right) it can be seen how
        
        
          much effort was taken to achieve the
        
        
          best possible’ refusal’, by continuing
        
        
          the injection well beyond the point
        
        
          where the specified 3 Lugeon criteria
        
        
          had been met. It can be observed that
        
        
          in this example the grouting continued
        
        
          for half an hour after the specified
        
        
          threshold, so that the refusal could be
        
        
          demonstrated over the last 30 minutes
        
        
          of injection.
        
        
          Working in this conservative manner
        
        
          achieved excellent results and ensured
        
        
          for the client that there was no require-
        
        
          ment for a further tertiary phase of
        
        
          treatment, which would certainly have
        
        
          added considerably to the cost and
        
        
          duration of the works.
        
        
          
            Grout curtain design
          
        
        
          The methodology and scope of the
        
        
          grouting works evolved throughout
        
        
          the duration of the project in response
        
        
          to ground conditions, and this evolu-
        
        
          tion was documented and controlled
        
        
          through the issue of detailed method
        
        
          statements and technical memoranda.
        
        
          The basic elements of the drilling and
        
        
          grouting design processes included:
        
        
          • Preparation of a 3D design model
        
        
          of borehole geometry for works
        
        
          phasing, management, control,
        
        
          planning, and reporting using
        
        
          CASTAUR programme
        
        
          • Generation of instructions for
        
        
          the drill crews using CASTAUR
        
        
          programme
        
        
          • Accurate setting out of drill hole
        
        
          locations
        
        
          • Drilling of boreholes to rock head
        
        
          and installation of guide /liner
        
        
          pipes and /or TaM pipes
        
        
          • Survey of as built alignment of drill
        
        
          holes using Boretrack /Maxibor
        
        
          • Revision of the 3D design model
        
        
          for as-built locations
        
        
          • Design of injection parameters for
        
        
          grouting, including GIN mode
        
        
          • Generation of electronic grouting
        
        
          and water testing instructions us-
        
        
          ing SPHINX, including selection
        
        
          of GIN value
        
        
          • Sequencing of grouting pro-
        
        
          grammes
        
        
          • Drilling of preliminary injection
        
        
          stages and water testing
        
        
          • Review of injection parameters and
        
        
          mixes using SPHINX and SCAN
        
        
          3-D
        
        
          • Drilling and injection in phases as
        
        
          detailed in sections under SPICE
        
        
          pump regulation
        
        
          
            Figure 2. Injection rate (blue), Pressure (red), and Equiv. Lugeon (green)
          
        
        
          
            values plotted against the injected volume (left). Injection rate, Pressure, and
          
        
        
          
            Equiv. Lugeon values plotted against the injection duration (right).